Windows 7 - One client (Server 2k8-R2/HyperV) will not sync with DPM

Asked By TroyH15 on 06-Jan-10 10:54 AM
We have been running DPM successfully for about a year now without any major
problems.  Recently we added a new server - a fairly robust PowerEdge that
will be housing 4 HyperV VMs.

For whatever reason, I cannot get anything but the HyperV "Initial Store" to
sync correctly.  I thought initially it might be a problem with the HyperV
machines, but it also fails to back up a small directory of files on the host
drive.

The oddest part about this is I really do not get an error.  It will try an
initial sync and run for a day or two and show very minimal data transferred.
(Generally no more than 100-200MB), but will continue to say it is running
for days.  If you cancel the job and look at the protection setup you will
see a large amount of data used  in the replica volume.

Unfortunately there are no errors logged on either the host or DPM server.
The jobs will eventually time-out with a 'replica inconsistent' message, but
it does not seem to provide any more information.

As an additional test, I re-associated the client machine with our other DPM
server and have experienced identical results.  So I am fairly confident that
the problem is on the host machine.   Other than Windows updates and
installing the HyperV role, the server is basically brand new.

Any ideas?  Any further details I can provide?


TroyH15 replied to TroyH15 on 06-Jan-10 02:26 PM
Figured it out... TCP offload was the problem.  Things seem to be working
great now.
techraider04 replied to TroyH15 on 06-Jan-10 07:36 PM
Chimney seems to be a problem with several technologies!
Chris replied to TroyH15 on 17-Mar-10 09:19 AM
Troy, can I ask what settings you changed to get this working?  was this on
the DPM server or the HyperV Host?

Thanks.

Chris